Custom Home Building Process
A typical 3,000 sq. ft home should be ready in about 6 months, depending upon any delays caused by weather, change orders or other special circumstances.



|
| Step | Timing |
| Lot Clear | Week 1 |
| Foundation | Weeks 2-4 |
| Framing, Dry-in Roof, Paint Exterior Trim | Weeks 5-9 |
| Rough-in HVAC and Electric, Plumbing Top-out, Speaker & Security Wiring | Weeks 10-11 |
| Exterior-Brick,Stone and/or Stucco, Sewer Tie-in, Septic Install & Roofing | Weeks 12-13 |
| Insulation | Week 14 |
| Dry Wall, Tape, Float & Texture | Weeks 15-16 |
| Floor Tile | Week 17 |
| Cabinets & Interior Trim | Weeks 18-19 |
| Interior Paint | Weeks 19-20 |
| Electrical, Plumbing & HVAC Final, Driveway & Sidewalk | Weeks 21-22 |
| Install Appliances & Hardware | Week 23 |
| Carpet & Wood Floor | Week 24 |
| Final Walk-Through & Touch Up | Week 25 |
| Move-In | Week 26 |
|